Submit Building Plans and Documents Requirements:
Detailed building plans prepared by a licensed architect.
Compliance with MIDC rules and the National Building Code (NBC 2005).
Supporting Documents:
Architect’s area statement.
Process flow chart.
Details about raw materials and finished goods.
Required approvals from the Maharashtra Pollution Control Board (MPCB).
Fire Officer Review Process:
MIDC Fire Officer reviews the submitted plans.
Classification of the building into a fire risk category (Green, Orange, Red) based on the planned industrial activity.
Fire Protection Fee – Fee Assessment:
After the review, a demand letter for Fire Protection Fund Fees is issued.
Fee calculated based on the size and height of the building.
Payment:
Payment must be made online following the instructions in the demand letter.
Provisional Fire NOC Issuance:
Upon payment of fees and validation of documents, MIDC issues a Provisional Fire NOC electronically.
Purpose:
This document allows construction to begin, indicating that basic fire safety requirements are met.
Validity
Duration:
The Provisional Fire NOC is valid until the completion of the building.
Final fire approval is needed after the construction and installation of fire safety systems.
These steps are involved in obtaining the MIDC Provisional Fire NOC Plan Approval process.
If you require additional details, please call us!
Regards
9819997500 – Atul
9819992310 – Sushant
www.midcwala.com